Perlite biofiltration (BF) for Stormwater Management
What follows is a design for biofiltration that was developed and promulgated
by the Department of Permitting Services, Water Resources Section, County of
Mongomery, Maryland, USA.
Biofiltration(BF)
The biofiltration methods described in the following section are based on the
bioretention design found in the Maryland Stormwater Design Manuel, and where
deemed appropriate, have been modified by the Montgomery County Department of
Permitting Services. DPS currently restricts the use of biofiltration (BF) for
the treatment of the water quality volume from catchment areas of 1.0 acre or
less. In addition, unless waived by DPS all biofiltration devices shall include
a PVC pipe underdrain system.
A. Facility Description
Biofiltration is a soil filtration system. Principal components of the system
(figures 1 & 2) include:
- a pretreatment grass filter strip,
- surface planting with woody and herbaceous plant species,
- a surface 50-80 mm thick mulch layer,
- a minimum 600 mm thick sandy loam or loamy sand soil-textured planting
soil media (See specifications),
- a 150 mm thick sand layer, and a perforated PVC pipe underdrainage
within a 400 mm thick gravel bed.
The entire system can generally fit into a relatively confined space, thus
making it well suited for incorporation within parking lot designs.
It is strongly recommended that stormwater runoff sheet flow through a grass
filter strip into the ponding area. A maximum 300 mm deep ponding depth has been
selected so as to reduce the likelihood of creating saturated-soil/anoxic
conditions within the system. The perforated PVC pipe underdrain system provides
proper drainage and aeration of the planting soil filter layer. Volumes above
the water quality volume will pass through the facility via a structural
overflow. Excess runoff that cannot be filtered is diverted away from the
biofiltration area via a graded grassed swale or similarly acceptable drainage
technique.
B. System Design Considerations
- Applicability
The biofiltration device is appropriate for drainage areas of I acre or
less, such as parking lots and building additions in highly visible areas.
Large biofiltration structures can be expensive to properly landscape and
maintain.
- Design Storm
The facility must be sized to provide storage for the required water
quality volume, Peak flows from the 10-year frequency storm must be safely
conveyed around the basin whenever possible. See Montgomery County Flow
Splitting Criteria.
- Groundwater
In general, the BF system cannot be located where the water table is within
2 meter of the ground surface. In situations where groundwater is encountered,
another method for water quality treatment should be considered.
C. Specifications and Details
Embankment Criteria
As shown in (figure 1) the BE utilizes an embankment with a minimum top width of
1200 mm, maximum 3:1 side slopes and a core trench. It is imperative that the
appropriate underdrain excavation, core trench, and all backfill and embankment
requirements are met, since these are permanent facilities. Refer to
"Construction Specifications for Shallow Facilities",
Sizing
The facility must be sized to store the required water quality volume
(WQV). As previously indicated, the maximum ponding depth above the filter
bed area is 400 mm. The facility shall be constructed to a 225 mm depth to
allow for settlement. Storage is computed above the surface of the facility.
The top of the filter media must be level across its entire surface.
Storage volume is determined from the top of the planting media to the crest of
the outlet weir or invert of the flow splitter overflow pipe, whichever is
lower.
Note: Biofiltration devices should not be located in areas where the water
table is within 2 m of the ground surface, within areas which contain mature
trees or other environmentally sensitive site features, or where existing slopes
exceed 15 percent.
To the extent possible, structures should have irregular outlines to blend
naturally into the environment. Rectangular is not natural
Stormwater Discharge Into Biofiltration Area
Pretreatment through a grass filter is preferred whenever possible. Pretreating
runoff may extend the life of the facility. A typical location for the
pre-treatment grass filter strip or swale is along the back portion of the
facility, adjacent to the planting media. Maximum velocities into the grass
filter may not exceed 1 m/s. Particular care must also be taken to prevent
erosion of the surface mulch layer. DPS recommends that maximum design storm
velocities across the filter bed area not exceed 0,3 m/s.
Overflow Weir Sizing Criteria
Design of the overflow weir, if required, is largely dependent upon the way
flows are delivered to the facility. Refer to "Montgomery County Flow Splitting
Criteria". Generally, the overflow weir design is as follows:
An overflow weir may not be required where a minimum of 0,3 m of freeboard
is provided above the 10-year water surface elevation in the facility. If an
overflow weir is necessary, it can be similar to a small emergency spillway and
must be located at existing ground level or in cut. If the facility is not fed
by a flow-splitter, size the weir to safely pass the full 10-year storm.
If the facility is fed by a flow-splitter, outlet weir sizes may be reduced,
with the outlet weir sized to safely pass whatever portion of the 10-year storm
is delivered to the facility. In this case, protection may be provided by
permanent turf reinforcement matting only. Utilization of turf reinforcement
matting should be considered wherever stream thermal concerns are an issue.
Individualized designs to safely pass either a flow-split 0 or the
10-year storm, both with 0,3 m of freeboard, are necessary. Provide a safe
non-erosive outlet below the outfall.
Underdrain Pipe
The underdrain pipe consists of 150 mm diameter schedule 40 or stronger
perforated PVC pipe at 0.00% slope. The underdrain pipe will be placed
within the gravel layer. 80 mm of gravel must be placed under the pipe, with
a minimum of 150 mm of gravel over the pipe. Perforations must be 10 mm in
diameter and must be located 100 mm on center, every 90 degrees around the
pipe. Perforated pipe must begin at least 1500 mm inside the filter media.
Filter fabric must not be wrapped around the underdrain pipe.
Access for cleaning all underdrain piping is needed. Clean-outs for each
pipe should extend 150 mm above the top of the planting media and have a
removable waterproof cap.
The required number of underdrain pipes is proportional to the surface
area of the biofiltration device. To determine the number of underdrain
pipes, multiply the surface area square meter by 0.2. This determines the
linear meter of piping required. Use a minimum of two pipes whenever
possible. For example, if the surface area of the biofiltration device is 45
square meter, then:
45 (0.2)= 9 meter
Thus, the requirement will be for two underdrain pipes, each 4,5 m long.
Underdrain pipes should be placed a minimum of 1,5 m apart.
Gravel Bed
The gravel layer surrounding the underdrain pipe(s) must meet MSHA size #7
(Table 901A), and must provide a minimum of 150 mm cover over the pipe(s), and
minimum 80 mm under the pipe. No geotextile or filter fabric is allowed anywhere
within the filter media (stone and sand).
Sand Bed
A minimum 150 mm fine aggregate sand layer shall be provided below the soil
filter/planting media. A sand window shall extend from the sand filter to the
surface of the planting media opposite from the inflow point. (figure 1). The
sand window will be a minimum of 1 m 2. ASTM C33 Fine Aggregate Concrete Sand is
required. Manufactured sand or stone dust is not acceptable.
Drawdown Time
Drawdown time must be designed to be between 12-24 hours. This will allow the
facility to be free to treat consecutive storms, while increasing the treatment
time to provide for adequate pollutant removal. Drawdown computations must be
submitted to DPS for review. A removable, watertight perforated underdrain cap
(25 mm minimum opening) may be used to achieve the drawdown requirement. The
perforation must be at the invert elevation of the underdrain pipe. In thermally
sensitive watersheds, a 12-hour drawdown time must be used.
Soil Filter/Planting Media
The planting media shall consist of 1/3 perlite, 1/3 compost and 1/3 topsoil .
The perlite shall be type 0560. The compost shall be high-grade compost free of
stones and partially composted woody material. The soil shall meet the following
minimum criteria: contain no more than 10% clay, 30 - 55% silt and 35 - 60%
sand. The soil shall be free of stones, stumps, roots or other similar objects
larger than 50 mm. 'The first layer of the planting media shall be lightly
tilled to mix it into the sand layer, so not to create a definitive boundary.
The planting material shall be flooded after placement . Any settlement that
occurs shall be filled back to the design elevation.
Mulch
The mulch layer is an important part of the BF. Much of the pollutant removal
capacity of the BF is within the mulch layer. The surface mulch layer will
consist of standard fine shredded aged hardwood mulch. The mulch should be
applied uniformly to a depth of 50-80 mm. Yearly replenishing may be necessary.
Pine bark is not acceptable.
Plant Materials
Plants, through their pollutant uptake and evapotranspiration of
stormwater runoff, play a key role in the overall effectiveness of the
biofiltration device. Both the number and type of tree and shrub plantings for
the system may vary, especially where aesthetics or other considerations are
critical to site development. While native plants are encouraged, they are not
always appropriate in all situations. While no hard planting rule exists, the
plants should be a mix of trees, shrubs and herbaceous materials. However, there
should be 2 to 3 shrubs planted per tree and herbaceous plantings shall make up
40 % of the total number of plants. Trees shall be a minimum of 2 % in. caliper,
shrubs shall be minimum 2 gal. size and herbaceous plants shall be a minimum 1
gal size. Mature plant canopy should cover 85 % of the BF. A landscape plan will
be required as part of the plan. The plan will be sealed by a registered
landscape architect. Since the plants are an integral part of the BE, no changes
to the approved landscape plan will be allowed without prior approval from DPS.
An 85% survival rate after 18 months will be required before the as built plan
is approved.